|
MODERN VENICE SUBDIVISION PROJECT TIMELINE
|
||
|
Date
|
Status
|
Description
|
| September 14, 2007 | n/a |
ATTENTION TO PORT ISABEL RESIDENTS, PARTICULARLY RESIDENTS IN THE DERRY AND MODERN VENICE (“FINGERS”) AREAS; THIS ANNOUNCEMENT SERVES TO INFORM THE PUBLIC THAT RLB, CONTRACTING INC. HAS GIVEN THE CITY OF PORT ISABEL NOTICE THAT THEY WILL BEGIN PRELIMINARY SITE WORK BEGINNING SEPTEMBER 14, 2007. INITIAL WORK WILL INCLUDE THE MOVEMENT OF EQUIPTMENT AND PREPARATION OF BERMS AND LEVEES ON THE DERRY SITE FOLLOWED BY DREGING ACTIVITIES WITHIN THE MAIN CHANNEL AND WESTERN INTERIOR CHANNEL IN MODERN
FOR MORE INFORMATION PLEASE |
|
|
||
| August 22, 2007 | In progress | NEW NOTICE TO COMMENCE DREDGING RLB Contracting, Inc. has been notified to commence work at the start of business on Monday August 27, 2007. Please note that dredging activities in the Main Channel and Western Interior Channel will begin within 30 calendar days from the Notice of Commencement. The time of completion for this project will be no longer than 75 days or by November 9, 2007. RLB will soon supply the City of |
|
|
||
| *Meeting Update | n/a | Monthly Modern Venice Committee meetings are temporarily on hold, coinciding with project commencement and receipt of survey work. Stay posted for another meeting in September or October. Date and time will be posted on this site and included on the monthly City of Port Isabel Calendar. |
|
|
||
| August 15, 2007 <Phase II Update> |
In progress | The City is working on obtaining survey work to verify the ownership of all channels in Modern Venice. This information will allow the City to move forward with the potential creation of a Public Improvement District to complete the uniform development of the entire Fingers area. Once the information delineating clear ownership has been obtained there will be a public workshop scheduled to discuss the options and details for Phase II. |
|
|
||
| August 15, 2007 <Phase I Update> |
In progress | Project activities are currently in the works, a contract for services with RLB Contractors, Inc. is being reviewed by the City Attorney. Once the contract is executed by both parties there is a maximum 30 day commencement period. Work is estimated to begin in September and the contractor is estimating that the job will take no longer than 75 days. |
|
|
||
| July 23, 2007 <Phase I Update> |
n/a | Port Isabel City Commission awards the Project Bid to RLB Contracting, Inc in the amount of $188,160. Dredging Project activities will include the following:
Main Entrance Channel: Area size is estimated to be approximately 1000 linear feet extending from the center of the channel into the Laguna Madre Bay. Channel will have an approximate top width of 82 feet, a required bottom width of 40 feet, side slope of 1 to 3 and a minimum depth of 6 feet at Mean Low Tide. Western Interior Channel: Area size is estimated to be approximately 800 linear feet in length. Channel will have an approximate top width of 35 feet, a required bottom width of 15 feet, side slope of 1 to 2 +I- and a minimum depth of 5 feet at Mean Low Tide. Refer to the following links for TECHNICAL SPECIFICATIONS and CONSTRUCTION DRAWINGS. |
|
|
||
| July 17, 2007 <Phase I Update> |
n/a | Modern Venice Committee meets with staff to open received bids. Two bids were received both of which propose to perform the project with a mechanical dredge with placement of spoils on the Derry Park site. Bid amounts are as follows: I) Rimrock Enterprises, Inc @ $259,000 plus $16.80 for each additional linear foot 2) RLB Contracting, Inc. @ $1 68,160 plus $50 for each additional linear foot. The Modern Venice Committee recommends that the Contract is awarded to RLB Contracting. They also make a recommendation that we include an additional 400 foot portion for the Western lnterior Channel to fully address the current unsafe navigability of the interior channel. |
|
|
||
| June 21, 2007 <Phase I Update> |
In progress | Dredging project preliminary information <document> |
|
|
||
| June 7, 2007 <Phase I Update> |
In progress | Department of the Army Permit #24482 <document> |
|
|
||
| June 2007 <Phase I Update> |
In progress | City receives approval of Individual Permit #24482 from the U.S. Army Corps of Engineers (see link). Dredging Project is properly advertised for bidding with a submittal deadline of July 17, 2007. |
|
|
||
| May 2, 2007 | May 2, 2007- TCEQ Water Quality Certification, Letter of consent regarding USACE Permit 24482 <document> | |
|
|
||
| April 19, 2007 | n/a | Notice of a Regular Meeting of the Port Isabel Modern Venice Committee. Location: Port Isabel City Commission Chambers Meeting room. 305 E. Maxan on Thursday, Apri l19, 2007 at 5:30 p.m. Agenda: <http://www.modernvenice.com/agendas/agenda041907.pdf> |
|
|
||
| April 16, 2007 | n/a | Phase 1 Update <document> |
|
|
||
| April 12, 2007 | n/a | Response to comments from Corps <document> |
|
|
||
| April 9, 2007 | n/a | Comments from Corps <document> |
|
|
||
| April 2, 2007 | In Progress | Individual permit request for Water Quality Certification <document> |
|
|
||
| April 2, 2007 | In Progress | Permit request for Water Quality Certification <document> |
|
|
||
| March 8, 2007 | In Progress | Army Corps of Engineers permit out for public notice. Status posted here: http://www.swg.usace.army.mil/reg/pn.asp. - On March 16, 2007 the permit went out for Public Comment. -The public comment period will end on April 2, 2007. If no negative comments are received that the permit will be issued after that date. |
|
|
||
| March 8, 2007 | Completed | Opinion No. GA-0528 Re: Whether a seawall funded from assessments levied pursuant to Local Government Code, chapter 372, subchapter A or B, may be built on privately-owned land. Opinion from the Attorney General- (Legality of installing seawalls on private property by means of a Public Improvement District) -The City of |
|
|
||
| February 15, 2007 | n/a | Public Hearing - Thursday, February 15, 2007 at the Port Isabel City Hall at 6:00 p.m. |
|
|
||
| In Progress | Phase I is an emergency action in response to the shoaling that has caused the subject area to become nearly un-navigable during low tide. Phase I includes dredging of the turning basin (the mouth of the channel, that provides access to the Laguna Madre Bay) and the drag lining of a western portion of the fingers, beginning at the mouth of the channel, continuing along the north side of Tarpon St. and terminating just north of Highway 100. In order to help build up the eroded portion of the undeveloped properties, during this phase, the spoil material will be placed on the undeveloped fingers (Tarpon and Bass St.) with approval of the property owners. <letter> |
|
|
|
||
| September 2, 2007 | In Progress | Phase II of this project is still likely to be accomplished by means of a PID (Public Improvement District) <pid document> Phase II will include installation of seawalls and infrastructure, i.e., streets and utilities to the undeveloped fingers. On September 6, 2006, the City submitted an opinion to the Attorney General verifying the legality of building seawalls on private property through PIDs. A response is anticipated by late March to early April. Our State Representative, Rene Oliveria, has also introduced bill H.B. 673 <bill> which adds authority to use a PID for seawalls on private property. We are awaiting a favorable opinion and/or the passage of this bill prior to Phase II. Once we have confirmation that we can legally move forward with the development of a PID, a series of public meetings/hearings will be scheduled accordingly. If the method of assessments is utilized then property owners will only be assessed for work that has been done on or affected their property. |
|
|
||
| February 9, 2007 | In Progress | The City holds an existing permit (General Permit #15926(02)/064) <permit> to maintain the intracoastal channels within the finger, however this does not include the channel north of Tarpon St., or the turning basin (mouth of the channel). These areas are under the jurisdiction of the U.S. Army Corps of Engineers. In order to proceed the Phase I the City of Port Isabel must get an individual permit from the Army Corps of Engineers to allow us to work within their jurisdiction. The individual permit approval is pending. U.S. Army Corps of Engineer Project Manager, Mark Patillo Conducted a site visit on February 9, 2007. The permit will be subject to a public review period of 15 days prior to issuance. Tha anticipated date to receive this permit is on or around March 1, 2007. |
|
|
||
| September 6, 2006 | Completed | Request for Attorney General's opinion regarding "Allowable Improvements Under Chapter 372 of the Texas Local Government Code. <document> |
|
|
||
|
September 2, 2005
|
Completed
|
General Permit - 15926(02)/064 <document>
|
|
|
||
| November 22, 2004 | Completed | Very preliminary construction cost information |
|
|
||
| August 2004 | Completed | Questionnaire results <more> |
|
|
||
|
July 27, 2004
|
Completed
|
Mayor Marchan's letter to Modern Venice Property owners <letter>
|
|
|
||
|
July 27, 2004
|
Completed
|
Modern Venice Improvement District Questionnaire mailed to Modern Venice Property owners (page 5 of letter) <questionnaire>
|
|
|
||
|
|
n/a
|
Proposed Improvement District <map>
|
|
|
||
|
1985
|
n/a
|
Modern Venice ca. 1985 <photo here>
|
|
|
||
|
early 1960s
|
n/a
|
Modern Venice in the early 1960s <photo here>
|
|
|
||
|
1928
|
n/a
|
The original 1928 plat of Port Isabel created by the Port Isabel Company shows the Modern Venice subdivision <plat here>
|
|
|
||
|
early 1900s
|
n/a
|
Modern Venice in the early 1900s <photo here>
|